Why microcement numbers are easy to misread
Microcement systems are often described by consumption rather than paint-style coverage. A data sheet might publish kilograms per square metre for two layers of a particular component. Another component in the same system may have a different rate. Treating the whole system as one generic “microcement coverage” number can therefore create a large purchasing error.
Per-layer and two-layer rates are not interchangeable
If a source says 1.1 kg/m² per layer and you plan two layers, the theoretical consumption is 2.2 kg/m² before waste. If the source instead says 2.2 kg/m² for two layers, that 2.2 already includes the coat count. This is the double-coat mistake SurfaceTally tries to make visible.
Preparation affects real consumption
Technical sheets commonly note that substrate levelling and preparation affect material use. A rough or uneven background can increase consumption even when the formula is correct. The calculator result should therefore be treated as a purchasing plan based on your entered rate, not a guarantee of site yield.
Separate base, finish and protective products
Use a line-item approach. Base coat material, finish coat material, primer and sealer should each have their own rate and package count. This makes it easier to spot which component is driving cost and whether a contractor quote includes the complete system.
A quick verification workflow
- Measure net surface area.
- Open the exact product data sheet.
- Confirm whether each rate is per layer or total system.
- Enter base and finish separately.
- Add an explicit waste allowance.
- Round to real package sizes only at the end.
Primary references to check
These sources illustrate the type of product-specific information discussed above. Always confirm the current document for the exact product you buy.
Practical scenario: base and finish packages round differently
A project can theoretically require 31 kg of base material and 9 kg of finish. If the base comes in 20 kg packs and the finish in 5 kg packs, the purchase is 40 kg of base and 10 kg of finish. Combining the two theoretical quantities into “40 kg of microcement” would look neat but would not correspond to anything that can actually be ordered.
Questions to answer before purchasing
- Did I double-count a multi-layer consumption figure?
- Are base and finish products separated?
- Did I round each product to its actual package size?